BALAJI TUNNEL II PACKAGE NO.9 - TURN KEY (EPC) CONTRACT
Project Name |
Balaji Tunnel-II Package No.9 - Turn Key (EPC) Contract |
Brief Description |
Package No.09/2006 Investigation, Design andEarth Work Excavation of GNSS Main Canal from From KM 254.000 to KM 262.100 including construction of CM & CD works, and Excavation and lining of Balaji Tunnel – II From KM 262.100 to KM KM 272.800 including all allied works under GNSS in Chittoor District, Andhra Pradesh State.(75% Share of Rs.18990.00 Lakhs) |
Employer |
I & CAD DEPARTMENT, Govt. of Andhra Pradesh |
Contract Value |
INR 1899.00 Millions |
Main Specifications of the Project |
Canal Length
Canal Discharge
Tunnel Length
Tunnel Required Discharge
Tunnel Designed Discharge
Tunnel Shape |
: 8.10 KM
: 74.95 Cumecs
: 10.70 KM
: 1233 Cusecs
: 34.95 Cumecs
: D-Shaped Lined |
|